Week four's primary focus was work on the original windows. Inventorying was required to identify where each window was located. Scraping, priming, pane replacement and glazing followed, and the windows will be installed in the near future. Meanwhile, shoring continued underneath the house in preparation for sill replacement and pier construction. Exterior sill was eventually replaced at the end of the week, with some interior sill replacement began as well.
Week five saw no visits of volunteers to Rampart, as Noelle (construction manager) and myself continued the process of leveling the house. The soffit and facia were also repaired, and the siding on the front elevation were completed.